Special

  • Ocean View Walkway

    The walkway at Seal Cove posed a challenge as the existing structure had rusted away and required full replacement. There was also a narrow access road and the walkway was suspended on the side of a cliff. Budget limitations for the replacement were also a challenge. The engineers concept was to remove paint and refinish…

  • Searsport Pier

    Type of Structure: Wooden pier with concrete deck The existing pier was severely deterorated. Tidle work was required, some of the replacement work was below low tide elevations. Bowman Constructors engineered a concrete placement method using sheeting and temporary pumps to place concrete mud slabs for the new wooden/stone pier structure. Bowman engaged marine barges…